{{definition|('''N-‘k’''') criterion denotes that the system is planned such that with all transmission facilities in service the system is in a secure state and for any ‘k’ credible contingency event(s) the system moves to a satisfactory state. If any further contingency events were to occur loads may have to be shed to return to a satisfactory state.  <ref>[https://ea.govt.nz/dmsdocument/3859 Transpower Main Transmission System Planning Guideline]</ref>}}The single contingencies to be considered under an N-1 criterion are:
 +
• loss of a single transmission circuit
 +
• loss of a single generator 
 +
• loss of an HVDC pole
 +
• loss of a single bus section
 +
• loss of an interconnecting transformer
 +
• loss of a single shunt connected reactive component, e.g. capacitor bank, SVC
 +
<br/>
 
==== [[Philippines]] ====
 
==== [[Philippines]] ====
 
{{definition|N-1 Criterion specifies that the Grid shall continue to operate in the Normal State following the loss of one Generating Unit, transmission line, or transformer. <ref>[http://www.erc.gov.ph/Files/Render/media/N-1OperationalCriteria.pdf Grid Management Committee Philippines / Section 6.2.2.3 of the Philippine Grid Code]</ref>}}<br/>
 
{{definition|N-1 Criterion specifies that the Grid shall continue to operate in the Normal State following the loss of one Generating Unit, transmission line, or transformer. <ref>[http://www.erc.gov.ph/Files/Render/media/N-1OperationalCriteria.pdf Grid Management Committee Philippines / Section 6.2.2.3 of the Philippine Grid Code]</ref>}}<br/>
Line 30: Line 39:
 
[[Category:Event]]
 
[[Category:Event]]
 
[[Category:Threat]]
 
[[Category:Threat]]
{{#set:defined by=Philippines|defined by=Switzerland|defined by=ENTSO-E}}
+
{{#set:defined by=New Zealand|defined by=Philippines|defined by=Switzerland|defined by=ENTSO-E}}

Revision as of 17:11, 5 February 2017

Definitions

European Definitions

ENTSO-E

(N-1)-Criterion: The rule according to which elements remaining in operation within TSO’s Responsibility Area after a Contingency from the Contingency List must be capable of accommodating the new operational situation without violating Operational Security Limits. [1]


National Definitions

New Zealand

(N-‘k’) criterion denotes that the system is planned such that with all transmission facilities in service the system is in a secure state and for any ‘k’ credible contingency event(s) the system moves to a satisfactory state. If any further contingency events were to occur loads may have to be shed to return to a satisfactory state. [2]

The single contingencies to be considered under an N-1 criterion are:

• loss of a single transmission circuit • loss of a single generator • loss of an HVDC pole • loss of a single bus section • loss of an interconnecting transformer • loss of a single shunt connected reactive component, e.g. capacitor bank, SVC

Philippines

N-1 Criterion specifies that the Grid shall continue to operate in the Normal State following the loss of one Generating Unit, transmission line, or transformer. [3]


Switzerland

(n-1)-Kriterium: Bezeichnet ein Prinzip, dessen Einhaltung den sicheren Netzbetrieb auch dann gewährleistet, wenn ein beliebiges einzelnes Element des Systems ausgefallen ist. [4]