The approval procedure to start a CMM utilisation project must be regarded from 2 main positions. | The approval procedure to start a CMM utilisation project must be regarded from 2 main positions. | ||
| − | 1) The mine owner | + | 1) The mine owner operates the utilisation plant |
| − | 2) A third party | + | 2) A third party operates the utilisation plant |
[[Bild:Timeline_project-development.jpg|framed |Timeline for project development]] | [[Bild:Timeline_project-development.jpg|framed |Timeline for project development]] | ||
| − | If the conditions for the project are clarified you can start the | + | If the conditions for the project are clarified you can start the planning of the '''[[Technical Procedure]]''' and the '''[[Emission Rights Procedure]]''' of the project. These two procedures are processed in parallel. |
| − | After the idea for the project | + | After the idea for the project has been created, the technical boundary conditions have to be checked at the mine first. Special features have to be observed: |
- CMM Quality | - CMM Quality | ||
| Zeile 24: | Zeile 24: | ||
- Any demand for electricity and heat on the mine | - Any demand for electricity and heat on the mine | ||
| − | - surplus methane (The surplus of CMM can be burned without energy recovery | + | - surplus methane (The surplus of CMM can be burned without energy recovery to reduce greenhouse gas emissions) |
| − | The legal constructions for the project depends mainly | + | The legal constructions for the project depends mainly on the kind of partners who setup the project. Often this process can last long at the beginning of the project especially if some partners are not familiar with the new technologies or the complicated regulations for an emission reduction project. To create a successful project all partners should understand the conditions. |
== Mine owner operats utlisation plant == | == Mine owner operats utlisation plant == | ||
Version vom 10. Mai 2012, 13:14 Uhr
Inhaltsverzeichnis
Approval procedure
The approval procedure to start a CMM utilisation project must be regarded from 2 main positions.
1) The mine owner operates the utilisation plant
2) A third party operates the utilisation plant
If the conditions for the project are clarified you can start the planning of the Technical Procedure and the Emission Rights Procedure of the project. These two procedures are processed in parallel.
After the idea for the project has been created, the technical boundary conditions have to be checked at the mine first. Special features have to be observed:
- CMM Quality
- Amount of CMM
- Availability of CMM
- Existing extraction systems
- Any demand for electricity and heat on the mine
- surplus methane (The surplus of CMM can be burned without energy recovery to reduce greenhouse gas emissions)
The legal constructions for the project depends mainly on the kind of partners who setup the project. Often this process can last long at the beginning of the project especially if some partners are not familiar with the new technologies or the complicated regulations for an emission reduction project. To create a successful project all partners should understand the conditions.
Mine owner operats utlisation plant
In this case the mine produce the CMM and utilised it. The products heat and power will be consumed by the mime itself. So there will be no real contracting problem to feeding of fuel and for the consumption of products.
Third party as Operator
If a thrid party is operator of the utilisation installation there are import additional matter should be regulated.
In this case the utilised CMM would be produced by a mine near by. So there mus be a contract about delivery of CMM to the utilisation installation. Specially for CMM there could not be a garanty for quantity and quality of the gas. The quality depence on the mining situation of the mine. There a big influences by:
- gas content in the digged coal
- Quantity of coal production
- market for coal
- interruption of coal producting by technical faults
Selling of products
The products of the utilisation shall be sold to the customer. Considering the situation the planned delivery date can be changed because of missing fuel. So all these factor has to be kept in mind by constructing a CMM project and related contracts.
Approval authorities in the different countries
| Country | Authority | Adress | WWW | |
|---|---|---|---|---|
| Germany | Federal Ministry for the Environment, Nature Conservation and Nuclear Safety (BMU) | Alexanderstrasse 1 Berlin | www.dehst.de | nicole.wilke@bmu.bund.de |
| Great Britain | Department of Energy and Climate Change (DECC) | Area 2D. 3 Whitehall Place London | www.decc.gov.uk | ben.lyon@decc.gsi.gov.uk |
| Kazakhstan | Administration of President of Kazakhstan | 102 office, 20 Abay Street Astana | www.climate.kz/rus | kbaigarin@nu.edu.kz |
| Poland | Ministry of the Environment | 52/54 Wawelska St. Warsaw | www.mos.gov.pl | tomasz.chruszczow@mos.gov.pl |
| Romania | Ministry of Environment and Forests | Libertatii Blvd. 12, Sector 5 Bucharest | www.mmediu.ro | narcis.jeler@mmediu.ro |
| Russia | Russian Federal Service for Hydrometeorology and Environmental Monitoring (Roshydromet) | Novovagan'kovsky Street 12 Moscow | www.mecom.ru | head@mecom.ru |
| Ukraine | State Environmental Investment Agency of Ukraine | 35, Urytskogo Str. Kiev | www.seia.gov.ua | yakubovskiy@seia.gov.ua |
More information about the national focal point and about the country http://unfccc.int/parties_and_observers/parties/items/2352.php